Finishing The Shop (was Heating The Shop)

mcoak

Registered
Registered
Joined
Apr 16, 2015
Messages
44
Changed the thread title to reflect what is going on.

Finished up the electrical service trench today. It ended up being 304 feet.

Next step is laying conduit in the trench. I'm guessing 2-3 days to get it all in place.

Wiring on the shop is roughed in. Should be inspected in the next two weeks. The inside work has to pass before the electrical company will come out to install the service.

Mitch
 
The conduit is in the trench and covered. Still waiting on the electrical inspection. Progress is slow. :eek 2:
 
Back
Top