Drywall is done. Overall I’m very pleased with the quality of work. Just a tedious process, and although it’s expected, it is messy. We’ll need to get a dumpster to haul away the scrap, but that’s over due given general construction waste.
It was also refreshing to deal with a contractor that didn’t have a contract, down payment, or other legal process. Paid them in full yesterday when they picked up their scaffolding.
Pictures of the pre-drywall framing did save my hind end already. Two outlets got covered over. Was able to pinpoint their location and cut them out without damaging any surface. I suppose I could whine to them about that but perfection isn’t cheap. Also, although it took quite a bit of flipping between pictures to trace wiring out of a subpanel, I was able to resolve an electrical wiring confusion. Had pulled most of the outlets and switches prior to drywall, and in putting them back something wasn’t right. Turned out to be two breakers that were mislabeled (swapped). That cost much of Sunday afternoon.
Much of the ceilings are already painted, and thanks to a high school friend from Duluth, Mn visiting, about half the outlets are replaced. Need more friends like that! We did take some time to play on the heavy equipment, dug out a flood water retention pond in one of the two gullies off the property hillside, and dropped a good sized dead tree in the woods.
Ferrite beads arrived so those will get tested later this morning, more painting, mopping /vacuuming up drywall dust, and reinstalling light fixtures for the next few days.
Token painted drywall picture. Ceiling will get some sort of wood panel/lath finish.